PROJECT NAME : Transmission System and Substation Development Project 6th Stage 1 (Lot 1-2) Project

 

 

Owner : Provincial Electricity Authority of Thailand (PEA)

Client : Provincial Electricity Authority of Thailand (PEA)

Location :  Central Provinces, Thailand

Period of Services : 2001 – 2003

Project Cost : Approx. 2,000 Million Baht

Scope of Services and Description of Duties :

 

ATT in association with Kyushu Electric Power Co., Ltd., Japan have been assigned to carry out engineering services for PEA’s Transmission and Substation Development Project 6th Stage 1 (Lot 1-2).

 

The objective is to approve the drawings and documents for the construction of PEA’s 19 substations, as well as to assist PEA in project management and supervision during construction and implement phase including day-to-day administration of the project.